The steel frame structure is well done, the sunshine board is spread on both sides of the frame, the wood interface is glued with waterproof sealing strips, and then pressed with aluminum plate, fixed with self-tapping screws, and sealed with a closure at the cross section of the plate. The decorative strip is to avoid soil entry in order to better fix the immovable plate, avoid being blown down by the wind, and the sealing strip is to better moisture-proof. The edges are closed to better keep the box warm and prevent soil from entering the surface.

Endurance board, sunshine board installation common problems:

First, the length of the plate does not exceed 8 meters, can be carried out cutting patchwork, the plate is too long will cause rupture.

Second, the plate is facing the Chaoyang area, because the plate is covered by the aging resistant UV layer, so as to achieve all normal life of the plate.

Third, the curved pipe interval of 1050M is appropriate, the interval is too large to harm the snow resistance and impact resistance of the plate, or indirectly cause the plate to break.

4. The solid core endurance plate is embedded with a telescopic hole, and the diameter of the telescopic hole should be more than 3 mm above the diameter of the drill tail wire.

5, the frame body to maintain stability, strong, to prevent the frame caused by damage to the plate.

6. The raw materials of the steel frame structure are consistent with the total area of the structure. 7, the whole process of installation to prevent contact with acid and alkali, partial alkali, oil soluble chemical concrete and other chemical substances.

8. The specifications and models of aluminum decorative strips are consistent with the thickness and total structural area of the plates.

9. The relative density of drilling tail wire is ≦ 30cm. The tightness level of drilling tail wire should be as high as possible, not too tight or too loose.

10, the installation of neutral glass glue to seal the gap in detail to avoid water seepage.

11. After the plate is sold, it should be properly stored in transit with light and careful care, and prevent immediate sun exposure during the storage period.

12, the protective film can be removed after the end of the construction, to avoid human factors scratching conditions, all conditions can not walk on the surface.

13, the bending degree of the plate according to the relative elevation or reduction of the thickness of the plate, the bending proportion of reference legend.

14, the structural frame can be selected according to the span size of aluminum profiles, under normal circumstances, the span of 3M below the selection of 20*40 or 25*50 rectangular square tube. The following span of 8 meters uses 40*80 or 50*100 rectangular square tubes. The span above 8 meters is proposed to make a double beam structure, or find a reliable qualification certificate enterprise to do the overall design.